Fulfilling a Single Generic Resource Requirement with Multiple Named Resources Purpose
When a generic Resource Requirement is fulfilled by multiple named resources, Project Operations intentionally leaves the generic resource assigned to the project tasks. In contrast to the single-resource fulfilment scenario described in Section #4, task assignments are not automatically redistributed when multiple named resources are booked against the same